Data center interconnection and substation planning

A 300 MW campus needs more than a signed site. It needs a utility that can serve it, a substation plan, and a realistic date for power. GridHub works between data center developers and the utilities that will serve them, so both sides plan from the same numbers.

01 / FOR DEVELOPERS

01 / FOR DEVELOPERS

What utilities need from a data center developer

Get the load request right the first time.

Utilities can’t study a load they don’t understand. GridHub helps developers put together what a utility asks for up front: load ramp schedule, peak demand, power quality and ride-through needs, redundancy, and a realistic in-service date. A complete request gives the utility fewer reasons to send it back with questions.

Load ramp & peak demand profile

Data center power requirements review

Ride-through & power quality requirements

Grid capacity & site screening

02 / FOR UTILITIES

02 / FOR UTILITIES

Large load interconnection for co-ops and municipal utilities

Serve the new load without putting existing members at risk.

A single campus can ask for more than a small utility’s entire peak. GridHub helps co-ops and municipal utilities review large load requests, set study scope, work through tariff and cost-allocation questions, and plan the substation and transmission upgrades the load will need.

Large load request review

Interconnection study scoping

Large load tariff considerations

Upgrade & cost allocation planning

03 / SUBSTATION PLANNING

03 / SUBSTATION PLANNING

Data center substation planning

The substation usually sets the schedule.

For most campuses the critical path runs through the substation: equipment lead times, land, and outage windows on the existing system. GridHub reviews substation configuration, redundancy and equipment strategy early, so long-lead transformers and breakers get ordered in time.

Substation configuration & redundancy review

Long-lead equipment strategy

Powered shell & phased energization planning

Grid connection schedule review

04 / FIELD EXPERIENCE

04 / FIELD EXPERIENCE

Field experience

Planning-stage work on 300 MW to 1 GW campuses.

Josue Sanchez, CPQ, MEM, has worked on the planning stage of large data center projects for major technology providers, with campuses from 300 MW to 1 GW. He spent years inside municipal utilities and more than half his career with major U.S. consulting firms, so he knows how a utility reads a load request.

300 MW to 1 GW campus planning

Developer and utility coordination

Power quality (CPQ certified)

Utility-side review of load requests

High-voltage substation insulators and bus work against a blue sky
High-voltage substation insulators and bus work against a blue sky
High-voltage substation insulators and bus work against a blue sky

HOW AN ENGAGEMENT WORKS

HOW AN ENGAGEMENT WORKS

Screen. Plan. Coordinate.

Screen: grid capacity and site fit before you commit

Plan: load profile, substation and upgrade plan with the utility

Coordinate: an independent go-between through energization

FAQ

Frequently asked questions

How long does data center interconnection take?

It depends on the utility, the size of the load, and whether transmission upgrades are needed. Substation and transformer lead times are often the longest part. GridHub helps you build a realistic schedule early, before it drives site decisions.

What is a large load interconnection study?

A study the utility runs to see whether its system can serve a new large load and what upgrades are needed. Scope varies by utility, but it usually covers capacity, substation needs and transmission impacts.

Do you work for developers or utilities?

Both, on separate engagements. GridHub advises data center developers on what utilities need, and helps utilities review and plan for large load requests.

Should a data center use behind-the-meter generation?

Sometimes, as a bridge to grid power or for resilience. It changes what the utility needs to plan for. GridHub helps you weigh it against a grid-tied connection from the utility’s point of view.

A clearer view of the evolving grid.

A clearer view of the evolving grid.

Independent perspectives on energy, engineering, and what comes next.

Independent perspectives on energy, engineering, and what comes next.

GridHub logo

Independent expertise. A stronger, more resilient grid.

© 2026 GridHub, LLC. All rights reserved.